First 750 kV transmission line, to be
commissioned by the end of 1984 is intended
as a reinforcement of the CMEA system
PEACE. Transmitted capability will be
about 2000 MVA at the begining. Line profile
i~ selected to avoid any limitation
in land utilisation for agriculture and
trafic. Technical parameters are given.
Line insulation test results are presented.
%0 Journal Article
%1 brociek1984poland
%A BROCIEK, S
%A CZAPLAK, W
%A JACZEWSKI, M
%A MALINOWSKI, J
%D 1984
%K 750kV-transmission line-construction line-insulation
%T 750 KV LINE IN POLAND
%X First 750 kV transmission line, to be
commissioned by the end of 1984 is intended
as a reinforcement of the CMEA system
PEACE. Transmitted capability will be
about 2000 MVA at the begining. Line profile
i~ selected to avoid any limitation
in land utilisation for agriculture and
trafic. Technical parameters are given.
Line insulation test results are presented.
@article{brociek1984poland,
abstract = {First 750 kV transmission line, to be
commissioned by the end of 1984 is intended
as a reinforcement of the CMEA system
PEACE. Transmitted capability will be
about 2000 MVA at the begining. Line profile
i~ selected to avoid any limitation
in land utilisation for agriculture and
trafic. Technical parameters are given.
Line insulation test results are presented.},
added-at = {2020-04-27T14:11:27.000+0200},
author = {BROCIEK, S and CZAPLAK, W and JACZEWSKI, M and MALINOWSKI, J},
biburl = {https://www.bibsonomy.org/bibtex/297cdf121eb96854080bb72f760a46b38/ceps},
interhash = {ae01d7e54a54d4ba919353a2ac3ce514},
intrahash = {97cdf121eb96854080bb72f760a46b38},
keywords = {750kV-transmission line-construction line-insulation},
timestamp = {2023-12-20T14:37:18.000+0100},
title = {750 KV LINE IN POLAND},
year = 1984
}