Project scheduling under uncertainty: Survey and research potentials

, and . European Journal of Operational Research, 165 (2): 289--306 (September 2005)
DOI: 10.1016/j.ejor.2004.04.002

Abstract

The vast majority of the research efforts in project scheduling assume complete information about the scheduling problem to be solved and a static deterministic environment within which the pre-computed baseline schedule will be executed. However, in the real world, project activities are subject to considerable uncertainty, which is gradually resolved during project execution. In this survey we review the fundamental approaches for scheduling under uncertainty: reactive scheduling, stochastic project scheduling, fuzzy project scheduling, robust (proactive) scheduling and sensitivity analysis. We discuss the potentials of these approaches for scheduling under uncertainty projects with deterministic network evolution structure.